Home/Construction Status

Construction Status

NE-4 is divided into 52 construction packages awarded to ~20 contractors. Status as of 28 March 2026.

Source: Wikipedia / NHAI. “Operational” = open to traffic. Percentage = civil work completion.

31
Packages operational
7
100% complete (pending opening)
14
Packages under construction
891 km
Operational distance

Delhi–Vadodara

31 packages·845 km total·22 operational
PkgLengthContractorStatus
118 kmAPCO InfratechOperational
229 kmAPCO InfratechOperational
332 kmCentrodorstroy IndiaOperational
437 kmHG InfraOperational
536 kmKCC BuildconOperational
631 kmKCC BuildconOperational
731 kmGawar ConstructionsOperational
833 kmHG InfraOperational
946 kmHG InfraOperational
1026 kmDhaya Maju Infra – Crescent EPC Projects98% complete
1112 kmLarsen & Toubro100% complete
1228 kmGR InfraOperational
1329 kmCDS Infra ProjectsOperational
1431 kmDhaya Maju Infra – Crescent EPC ProjectsOperational
158 kmDilip Buildcon – Altis Holding Corp88% complete
1625 kmDRA InfraconOperational
1732 kmJiangXi Construction – MKC InfraOperational
1833 kmGR InfraOperational
1930 kmJiangXi Construction – MKC InfraOperational
2025 kmGHV IndiaOperational
2130 kmGR InfraOperational
2225 kmLarsen & ToubroOperational
2325 kmGR InfraOperational
2421 kmGR InfraOperational
2523 kmGR InfraOperational
2630 kmAtlas Construction – NKC95% complete
2729 kmGHV India100% complete
2826 kmGHV India100% complete
2923 kmPNC Infratech100% complete
3022 kmPatel Infrastructure100% complete
3119 kmPNC Infratech100% complete

Vadodara–Virar–JNPT Spurs

18 packages·448 km total·7 operational
PkgLengthContractorStatus
V124 kmIRB InfraOperational
V232 kmIRCONOperational
V331 kmPatel InfrastructureOperational
V413 kmAshoka BuildconOperational
V525 kmSadbhav Engineering – Gawar ConstructionOperational
V637 kmGR InfraOperational
V728 kmIRB InfraOperational
V835 kmRoadways Solutions India5% complete
V927 kmRoadways Solutions India10% complete
V1025 kmRoadways Solutions India43% complete
V1126 kmRKC Infrabuild100% complete
V1226 kmMontecarlo95% complete
V1324 kmGR Infra92% complete
V1417 kmIRCON88% complete
V1523 kmAgroh Infrastructure95% complete
V1627 kmShivalaya Construction87% complete
V1710 kmIRCON93% complete
V1818 kmMerged with MSRDC CorridorMerged / N/A

DND–Faridabad–KMP Spur

4 packages·91 km total·2 operational
PkgLengthContractorStatus
D19 kmDRA Infracon98% complete
D225 kmDRA InfraconOperational
D326 kmDRA InfraconOperational
J131 kmAPCO Infratech64% complete

Overall completion target

The entire Delhi–Vadodara stretch (845 km) is expected to be fully complete by December 2026. The Vadodara–Mumbai section is targeted for full operation in 2027–28.